Completion of Sewerage Works for the Municipality of Montemor -o- Velho

Pinto & Braz, Lda has completed the Rede de Esgotos de Arazede – Fase E – Bebedouro” and “ Rede de Esgotos de Arazede – Fase F – Resgatados” works for the Municipality of Montemor-o Velho. 

These projects had as their particularity the execution of sanitation networks for the Bebedouro and Resgatados villages through the Vacuum sewage system. 14 730 ml Vacuum collectors were built, 215 vacuum boxes to which about 300 home extensions are connected. A vacuum plant was built to which the entire network of collectors of Resgatados and Bebedouro is connected. In the week from 07/22/2019 to 07/26/2019 all tests and trials of the system were performed successfully. Mr. Meno Schinas was present, as technician of our business partner (Qua-vac - vacuum systems) of the Vacuum Sanitation System, the commissioning of the works was carried out and the training of the representatives of the developer was carried out.